{"id":1033,"date":"2010-10-30T06:37:34","date_gmt":"2010-10-30T14:37:34","guid":{"rendered":"http:\/\/lookforwardconsulting.com\/?p=1033"},"modified":"2024-03-05T10:52:20","modified_gmt":"2024-03-05T10:52:20","slug":"how-to-use-a-sprint-burndown-chart","status":"publish","type":"post","link":"https:\/\/thescrumacademy.com\/es\/2010\/10\/30\/how-to-use-a-sprint-burndown-chart\/","title":{"rendered":"How to Use a Sprint Burndown Chart"},"content":{"rendered":"<p><a href=\"http:\/\/thescrumacademy.com\/wp-content\/uploads\/2010\/10\/Figure4.jpg\"><img decoding=\"async\" class=\"lazyload alignleft size-full wp-image-1034\" title=\"Sprint Burndown chart\" src=\"http:\/\/thescrumacademy.com\/wp-content\/uploads\/2010\/10\/Figure4.jpg\" data-orig-src=\"http:\/\/thescrumacademy.com\/wp-content\/uploads\/2010\/10\/Figure4.jpg\" alt=\"\" width=\"596\" height=\"368\" srcset=\"data:image\/svg+xml,%3Csvg%20xmlns%3D%27http%3A%2F%2Fwww.w3.org%2F2000%2Fsvg%27%20width%3D%27596%27%20height%3D%27368%27%20viewBox%3D%270%200%20596%20368%27%3E%3Crect%20width%3D%27596%27%20height%3D%27368%27%20fill-opacity%3D%220%22%2F%3E%3C%2Fsvg%3E\" data-srcset=\"https:\/\/thescrumacademy.com\/wp-content\/uploads\/2010\/10\/Figure4-300x185.jpg 300w, https:\/\/thescrumacademy.com\/wp-content\/uploads\/2010\/10\/Figure4-500x309.jpg 500w, https:\/\/thescrumacademy.com\/wp-content\/uploads\/2010\/10\/Figure4-700x432.jpg 700w, https:\/\/thescrumacademy.com\/wp-content\/uploads\/2010\/10\/Figure4.jpg 993w\" data-sizes=\"auto\" data-orig-sizes=\"(max-width: 596px) 100vw, 596px\" \/><\/a><\/p>\n<p>A Sprint Burndown chart is a simple tool used by <img decoding=\"async\" class=\"lazyload alignleft size-full wp-image-1034\" title=\"Sprint Burndown chart\" src=\"http:\/\/thescrumacademy.com\/wp-content\/uploads\/2010\/10\/Figure4.jpg\" data-orig-src=\"http:\/\/thescrumacademy.com\/wp-content\/uploads\/2010\/10\/Figure4.jpg\" alt=\"\" width=\"596\" height=\"368\" srcset=\"data:image\/svg+xml,%3Csvg%20xmlns%3D%27http%3A%2F%2Fwww.w3.org%2F2000%2Fsvg%27%20width%3D%27596%27%20height%3D%27368%27%20viewBox%3D%270%200%20596%20368%27%3E%3Crect%20width%3D%27596%27%20height%3D%27368%27%20fill-opacity%3D%220%22%2F%3E%3C%2Fsvg%3E\" data-srcset=\"https:\/\/thescrumacademy.com\/wp-content\/uploads\/2010\/10\/Figure4-300x185.jpg 300w, https:\/\/thescrumacademy.com\/wp-content\/uploads\/2010\/10\/Figure4-500x309.jpg 500w, https:\/\/thescrumacademy.com\/wp-content\/uploads\/2010\/10\/Figure4-700x432.jpg 700w, https:\/\/thescrumacademy.com\/wp-content\/uploads\/2010\/10\/Figure4.jpg 993w\" data-sizes=\"auto\" data-orig-sizes=\"(max-width: 596px) 100vw, 596px\" \/>the Team to provide a measurement on how close they are to meeting the Sprint Goal by the end of the Sprint. \u00a0Burndown charts are common in Scrum and are simply the\u00a0trend of work remaining across time in a Sprint, a release, or a product.\u00a0 The source of raw data for a burndown is the Sprint Backlog, with work remaining tracked on the vertical axis and the time period (days of a Sprint) tracked on the horizontal axis. \u00a0The Sprint Backlog is just the\u00a0collection of tasks which represent the Team\u2019s current understanding of how they plan to achieve the Sprint Goal.<\/p>\n<p>Sprint Burndown charts are evolving and active artifacts on a Scrum Team. \u00a0When a Sprint Backlog item &#8211;\u00a0a single task or deliverable defined and estimated by a Team member &#8211;\u00a0moves from in progress to complete, it\u2019s estimate is removed from the total estimated work remaining in the Sprint. \u00a0There is not a lot of value estimating how many hours are remaining &#8211; the work is either done or not. \u00a0However, as a Team further refines their understanding of what needs to be done, creating new Sprint Backlog and estimates are added to the total estimated work remaining. \u00a0It is important that the Sprint Backlog and Sprint Burndown chart stay in sync since the graph gives visibility on the Team&#8217;s understanding of the work.<\/p>\n<p>There are four common patterns in most Sprint Burndown charts.\u00a0 The sample chart above, based on real Sprint data from a 2010 Scrum Team, displays all of these patterns.<\/p>\n<ol>\n<li>The Sprint Burndown goes flat, as seen on Days #4 and #5.<\/li>\n<li>The projected trend (or slope) has the Team completing the Sprint after the timebox expires, as shown between Days #6 and #7.<\/li>\n<li>New work is added late in the Sprint, as indicated on Day #6.<\/li>\n<li>A large delta between the actual progress of the Team and the predicted progress of the Team (as if they had burned down an equal amount of work each day), as seen between Days #5 to #9.<\/li>\n<\/ol>\n<p>In all these cases, these patterns provide an opportunity for the Team to discuss what is really going on and provide an explanation.\u00a0 If the Team is confident they can still fulfill the Sprint Goal regardless of how the data is displayed in the Sprint Burndown chart, the Product Owner and the ScrumMaster should always respect the judgement of the Team.\u00a0 Recall, the Team commits to delivering the Sprint Goal at the Sprint Review, not to deliver the Sprint Backlog items.<\/p>\n","protected":false},"excerpt":{"rendered":"<p>A Sprint Burndown chart is a simple tool used by the Team to provide a measurement on how close they are to meeting the Sprint Goal by the end of  [&#8230;]<\/p>\n","protected":false},"author":1,"featured_media":4091,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"_monsterinsights_skip_tracking":false,"_monsterinsights_sitenote_active":false,"_monsterinsights_sitenote_note":"","_monsterinsights_sitenote_category":0,"_price":"","_stock":"","_tribe_ticket_header":"","_tribe_default_ticket_provider":"","_tribe_ticket_capacity":"0","_ticket_start_date":"","_ticket_end_date":"","_tribe_ticket_show_description":"","_tribe_ticket_show_not_going":false,"_tribe_ticket_use_global_stock":"","_tribe_ticket_global_stock_level":"","_global_stock_mode":"","_global_stock_cap":"","_tribe_rsvp_for_event":"","_tribe_ticket_going_count":"","_tribe_ticket_not_going_count":"","_tribe_tickets_list":"[]","_tribe_ticket_has_attendee_info_fields":false,"footnotes":""},"categories":[208,90,7,205,171,82,22,25,46,213,88,10,77,34,209,206,29,214,212,210,44,5,71,215,8,217,91],"tags":[],"class_list":["post-1033","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-advanced-practitioners","category-agile-metrics","category-agile-scrum","category-beginners","category-best-of-the-best","category-burndown-charts","category-coaching","category-communication","category-daily-scrum","category-daily-standup","category-definition-of-done","category-developers","category-distributed-teams","category-documentation","category-leaders","category-practitioners","category-product-owner","category-scrum-artifacts","category-scrum-ceremonies","category-scrum-framework","category-scrum-master","category-scrum-methodology","category-scrum-planning","category-scrum-team","category-scrum-tools","category-scrum-values","category-sprint-goal"],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v27.4 - https:\/\/yoast.com\/product\/yoast-seo-wordpress\/ -->\n<title>Using a Sprint Burndown Chart<\/title>\n<meta name=\"description\" content=\"A Sprint Burndown chart is a simple tool used by the Team to provide a measurement on how close they are to meeting the Sprint Goal by the end of the Sprint.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/thescrumacademy.com\/es\/2010\/10\/30\/how-to-use-a-sprint-burndown-chart\/\" \/>\n<meta property=\"og:locale\" content=\"es_ES\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Using a Sprint Burndown Chart\" \/>\n<meta property=\"og:description\" content=\"A Sprint Burndown chart is a simple tool used by the Team to provide a measurement on how close they are to meeting the Sprint Goal by the end of the Sprint.\" \/>\n<meta property=\"og:url\" content=\"https:\/\/thescrumacademy.com\/es\/2010\/10\/30\/how-to-use-a-sprint-burndown-chart\/\" \/>\n<meta property=\"og:site_name\" content=\"The Scrum Academy\" \/>\n<meta property=\"article:published_time\" content=\"2010-10-30T14:37:34+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2024-03-05T10:52:20+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/thescrumacademy.com\/wp-content\/uploads\/2010\/10\/Screen-Shot-2019-10-25-at-6.10.29-PM.png\" \/>\n\t<meta property=\"og:image:width\" content=\"211\" \/>\n\t<meta property=\"og:image:height\" content=\"234\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/png\" \/>\n<meta name=\"author\" content=\"Carlton Nettleton\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Escrito por\" \/>\n\t<meta name=\"twitter:data1\" content=\"Carlton Nettleton\" \/>\n\t<meta name=\"twitter:label2\" content=\"Tiempo de lectura\" \/>\n\t<meta name=\"twitter:data2\" content=\"2 minutos\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\\\/\\\/thescrumacademy.com\\\/es\\\/2010\\\/10\\\/30\\\/how-to-use-a-sprint-burndown-chart\\\/#article\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/thescrumacademy.com\\\/es\\\/2010\\\/10\\\/30\\\/how-to-use-a-sprint-burndown-chart\\\/\"},\"author\":{\"name\":\"Carlton Nettleton\",\"@id\":\"https:\\\/\\\/thescrumacademy.com\\\/es\\\/#\\\/schema\\\/person\\\/2a0fb199044ecd4af3704c734747fc6a\"},\"headline\":\"How to Use a Sprint Burndown Chart\",\"datePublished\":\"2010-10-30T14:37:34+00:00\",\"dateModified\":\"2024-03-05T10:52:20+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/thescrumacademy.com\\\/es\\\/2010\\\/10\\\/30\\\/how-to-use-a-sprint-burndown-chart\\\/\"},\"wordCount\":434,\"commentCount\":0,\"image\":{\"@id\":\"https:\\\/\\\/thescrumacademy.com\\\/es\\\/2010\\\/10\\\/30\\\/how-to-use-a-sprint-burndown-chart\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/thescrumacademy.com\\\/wp-content\\\/uploads\\\/2010\\\/10\\\/Screen-Shot-2019-10-25-at-6.10.29-PM.png\",\"articleSection\":[\"Advanced Practitioners\",\"Agile Metrics\",\"Agile Scrum\",\"Beginners\",\"Best of the Best\",\"Burndown Charts\",\"Coaching\",\"Communication\",\"Daily Scrum\",\"Daily Standup\",\"Definition of Done\",\"Developers\",\"Distributed Teams\",\"Documentation\",\"Leaders\",\"Practitioners\",\"Product Owner\",\"Scrum Artifacts\",\"Scrum Ceremonies\",\"Scrum Framework\",\"Scrum Master\",\"Scrum Methodology\",\"Scrum Planning\",\"Scrum Team\",\"Scrum Tools\",\"Scrum Values\",\"Sprint Goal\"],\"inLanguage\":\"es\",\"potentialAction\":[{\"@type\":\"CommentAction\",\"name\":\"Comment\",\"target\":[\"https:\\\/\\\/thescrumacademy.com\\\/es\\\/2010\\\/10\\\/30\\\/how-to-use-a-sprint-burndown-chart\\\/#respond\"]}]},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/thescrumacademy.com\\\/es\\\/2010\\\/10\\\/30\\\/how-to-use-a-sprint-burndown-chart\\\/\",\"url\":\"https:\\\/\\\/thescrumacademy.com\\\/es\\\/2010\\\/10\\\/30\\\/how-to-use-a-sprint-burndown-chart\\\/\",\"name\":\"Using a Sprint Burndown Chart\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/thescrumacademy.com\\\/es\\\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\\\/\\\/thescrumacademy.com\\\/es\\\/2010\\\/10\\\/30\\\/how-to-use-a-sprint-burndown-chart\\\/#primaryimage\"},\"image\":{\"@id\":\"https:\\\/\\\/thescrumacademy.com\\\/es\\\/2010\\\/10\\\/30\\\/how-to-use-a-sprint-burndown-chart\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/thescrumacademy.com\\\/wp-content\\\/uploads\\\/2010\\\/10\\\/Screen-Shot-2019-10-25-at-6.10.29-PM.png\",\"datePublished\":\"2010-10-30T14:37:34+00:00\",\"dateModified\":\"2024-03-05T10:52:20+00:00\",\"author\":{\"@id\":\"https:\\\/\\\/thescrumacademy.com\\\/es\\\/#\\\/schema\\\/person\\\/2a0fb199044ecd4af3704c734747fc6a\"},\"description\":\"A Sprint Burndown chart is a simple tool used by the Team to provide a measurement on how close they are to meeting the Sprint Goal by the end of the Sprint.\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/thescrumacademy.com\\\/es\\\/2010\\\/10\\\/30\\\/how-to-use-a-sprint-burndown-chart\\\/#breadcrumb\"},\"inLanguage\":\"es\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/thescrumacademy.com\\\/es\\\/2010\\\/10\\\/30\\\/how-to-use-a-sprint-burndown-chart\\\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"es\",\"@id\":\"https:\\\/\\\/thescrumacademy.com\\\/es\\\/2010\\\/10\\\/30\\\/how-to-use-a-sprint-burndown-chart\\\/#primaryimage\",\"url\":\"https:\\\/\\\/thescrumacademy.com\\\/wp-content\\\/uploads\\\/2010\\\/10\\\/Screen-Shot-2019-10-25-at-6.10.29-PM.png\",\"contentUrl\":\"https:\\\/\\\/thescrumacademy.com\\\/wp-content\\\/uploads\\\/2010\\\/10\\\/Screen-Shot-2019-10-25-at-6.10.29-PM.png\",\"width\":211,\"height\":234},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/thescrumacademy.com\\\/es\\\/2010\\\/10\\\/30\\\/how-to-use-a-sprint-burndown-chart\\\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\\\/\\\/thescrumacademy.com\\\/es\\\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"How to Use a Sprint Burndown Chart\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/thescrumacademy.com\\\/es\\\/#website\",\"url\":\"https:\\\/\\\/thescrumacademy.com\\\/es\\\/\",\"name\":\"The Scrum Academy\",\"description\":\"Everyone anywhere can do better Scrum\",\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/thescrumacademy.com\\\/es\\\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"es\"},{\"@type\":\"Person\",\"@id\":\"https:\\\/\\\/thescrumacademy.com\\\/es\\\/#\\\/schema\\\/person\\\/2a0fb199044ecd4af3704c734747fc6a\",\"name\":\"Carlton Nettleton\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"es\",\"@id\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/6d69c37c349230a49a1ec6c77c21c4b35043de9fbcce8a202d61f707025cd537?s=96&d=mm&r=g\",\"url\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/6d69c37c349230a49a1ec6c77c21c4b35043de9fbcce8a202d61f707025cd537?s=96&d=mm&r=g\",\"contentUrl\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/6d69c37c349230a49a1ec6c77c21c4b35043de9fbcce8a202d61f707025cd537?s=96&d=mm&r=g\",\"caption\":\"Carlton Nettleton\"},\"description\":\"My name is Carlton Nettleton and I am the President of Look Forward Consulting. I am an international speaker, trainer and author of the book, Fourteen Observations of Good Scrum Practice and my book has been translated into Spanish. My passion is to share my excitement, enthusiasm and encouragement with teams and organizations as they reach for higher levels of performance and engagement. My business is to help your business grow and flourish.\",\"url\":\"https:\\\/\\\/thescrumacademy.com\\\/es\\\/author\\\/admin\\\/\"}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Using a Sprint Burndown Chart","description":"A Sprint Burndown chart is a simple tool used by the Team to provide a measurement on how close they are to meeting the Sprint Goal by the end of the Sprint.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/thescrumacademy.com\/es\/2010\/10\/30\/how-to-use-a-sprint-burndown-chart\/","og_locale":"es_ES","og_type":"article","og_title":"Using a Sprint Burndown Chart","og_description":"A Sprint Burndown chart is a simple tool used by the Team to provide a measurement on how close they are to meeting the Sprint Goal by the end of the Sprint.","og_url":"https:\/\/thescrumacademy.com\/es\/2010\/10\/30\/how-to-use-a-sprint-burndown-chart\/","og_site_name":"The Scrum Academy","article_published_time":"2010-10-30T14:37:34+00:00","article_modified_time":"2024-03-05T10:52:20+00:00","og_image":[{"width":211,"height":234,"url":"https:\/\/thescrumacademy.com\/wp-content\/uploads\/2010\/10\/Screen-Shot-2019-10-25-at-6.10.29-PM.png","type":"image\/png"}],"author":"Carlton Nettleton","twitter_card":"summary_large_image","twitter_misc":{"Escrito por":"Carlton Nettleton","Tiempo de lectura":"2 minutos"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/thescrumacademy.com\/es\/2010\/10\/30\/how-to-use-a-sprint-burndown-chart\/#article","isPartOf":{"@id":"https:\/\/thescrumacademy.com\/es\/2010\/10\/30\/how-to-use-a-sprint-burndown-chart\/"},"author":{"name":"Carlton Nettleton","@id":"https:\/\/thescrumacademy.com\/es\/#\/schema\/person\/2a0fb199044ecd4af3704c734747fc6a"},"headline":"How to Use a Sprint Burndown Chart","datePublished":"2010-10-30T14:37:34+00:00","dateModified":"2024-03-05T10:52:20+00:00","mainEntityOfPage":{"@id":"https:\/\/thescrumacademy.com\/es\/2010\/10\/30\/how-to-use-a-sprint-burndown-chart\/"},"wordCount":434,"commentCount":0,"image":{"@id":"https:\/\/thescrumacademy.com\/es\/2010\/10\/30\/how-to-use-a-sprint-burndown-chart\/#primaryimage"},"thumbnailUrl":"https:\/\/thescrumacademy.com\/wp-content\/uploads\/2010\/10\/Screen-Shot-2019-10-25-at-6.10.29-PM.png","articleSection":["Advanced Practitioners","Agile Metrics","Agile Scrum","Beginners","Best of the Best","Burndown Charts","Coaching","Communication","Daily Scrum","Daily Standup","Definition of Done","Developers","Distributed Teams","Documentation","Leaders","Practitioners","Product Owner","Scrum Artifacts","Scrum Ceremonies","Scrum Framework","Scrum Master","Scrum Methodology","Scrum Planning","Scrum Team","Scrum Tools","Scrum Values","Sprint Goal"],"inLanguage":"es","potentialAction":[{"@type":"CommentAction","name":"Comment","target":["https:\/\/thescrumacademy.com\/es\/2010\/10\/30\/how-to-use-a-sprint-burndown-chart\/#respond"]}]},{"@type":"WebPage","@id":"https:\/\/thescrumacademy.com\/es\/2010\/10\/30\/how-to-use-a-sprint-burndown-chart\/","url":"https:\/\/thescrumacademy.com\/es\/2010\/10\/30\/how-to-use-a-sprint-burndown-chart\/","name":"Using a Sprint Burndown Chart","isPartOf":{"@id":"https:\/\/thescrumacademy.com\/es\/#website"},"primaryImageOfPage":{"@id":"https:\/\/thescrumacademy.com\/es\/2010\/10\/30\/how-to-use-a-sprint-burndown-chart\/#primaryimage"},"image":{"@id":"https:\/\/thescrumacademy.com\/es\/2010\/10\/30\/how-to-use-a-sprint-burndown-chart\/#primaryimage"},"thumbnailUrl":"https:\/\/thescrumacademy.com\/wp-content\/uploads\/2010\/10\/Screen-Shot-2019-10-25-at-6.10.29-PM.png","datePublished":"2010-10-30T14:37:34+00:00","dateModified":"2024-03-05T10:52:20+00:00","author":{"@id":"https:\/\/thescrumacademy.com\/es\/#\/schema\/person\/2a0fb199044ecd4af3704c734747fc6a"},"description":"A Sprint Burndown chart is a simple tool used by the Team to provide a measurement on how close they are to meeting the Sprint Goal by the end of the Sprint.","breadcrumb":{"@id":"https:\/\/thescrumacademy.com\/es\/2010\/10\/30\/how-to-use-a-sprint-burndown-chart\/#breadcrumb"},"inLanguage":"es","potentialAction":[{"@type":"ReadAction","target":["https:\/\/thescrumacademy.com\/es\/2010\/10\/30\/how-to-use-a-sprint-burndown-chart\/"]}]},{"@type":"ImageObject","inLanguage":"es","@id":"https:\/\/thescrumacademy.com\/es\/2010\/10\/30\/how-to-use-a-sprint-burndown-chart\/#primaryimage","url":"https:\/\/thescrumacademy.com\/wp-content\/uploads\/2010\/10\/Screen-Shot-2019-10-25-at-6.10.29-PM.png","contentUrl":"https:\/\/thescrumacademy.com\/wp-content\/uploads\/2010\/10\/Screen-Shot-2019-10-25-at-6.10.29-PM.png","width":211,"height":234},{"@type":"BreadcrumbList","@id":"https:\/\/thescrumacademy.com\/es\/2010\/10\/30\/how-to-use-a-sprint-burndown-chart\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/thescrumacademy.com\/es\/"},{"@type":"ListItem","position":2,"name":"How to Use a Sprint Burndown Chart"}]},{"@type":"WebSite","@id":"https:\/\/thescrumacademy.com\/es\/#website","url":"https:\/\/thescrumacademy.com\/es\/","name":"The Scrum Academy","description":"Everyone anywhere can do better Scrum","potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/thescrumacademy.com\/es\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"es"},{"@type":"Person","@id":"https:\/\/thescrumacademy.com\/es\/#\/schema\/person\/2a0fb199044ecd4af3704c734747fc6a","name":"Carlton Nettleton","image":{"@type":"ImageObject","inLanguage":"es","@id":"https:\/\/secure.gravatar.com\/avatar\/6d69c37c349230a49a1ec6c77c21c4b35043de9fbcce8a202d61f707025cd537?s=96&d=mm&r=g","url":"https:\/\/secure.gravatar.com\/avatar\/6d69c37c349230a49a1ec6c77c21c4b35043de9fbcce8a202d61f707025cd537?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/6d69c37c349230a49a1ec6c77c21c4b35043de9fbcce8a202d61f707025cd537?s=96&d=mm&r=g","caption":"Carlton Nettleton"},"description":"My name is Carlton Nettleton and I am the President of Look Forward Consulting. I am an international speaker, trainer and author of the book, Fourteen Observations of Good Scrum Practice and my book has been translated into Spanish. My passion is to share my excitement, enthusiasm and encouragement with teams and organizations as they reach for higher levels of performance and engagement. My business is to help your business grow and flourish.","url":"https:\/\/thescrumacademy.com\/es\/author\/admin\/"}]}},"_links":{"self":[{"href":"https:\/\/thescrumacademy.com\/es\/wp-json\/wp\/v2\/posts\/1033","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/thescrumacademy.com\/es\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/thescrumacademy.com\/es\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/thescrumacademy.com\/es\/wp-json\/wp\/v2\/users\/1"}],"replies":[{"embeddable":true,"href":"https:\/\/thescrumacademy.com\/es\/wp-json\/wp\/v2\/comments?post=1033"}],"version-history":[{"count":0,"href":"https:\/\/thescrumacademy.com\/es\/wp-json\/wp\/v2\/posts\/1033\/revisions"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/thescrumacademy.com\/es\/wp-json\/wp\/v2\/media\/4091"}],"wp:attachment":[{"href":"https:\/\/thescrumacademy.com\/es\/wp-json\/wp\/v2\/media?parent=1033"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/thescrumacademy.com\/es\/wp-json\/wp\/v2\/categories?post=1033"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/thescrumacademy.com\/es\/wp-json\/wp\/v2\/tags?post=1033"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}